before 7 months | EMIL EGGER AG

Efficient bridge replacement for the ASTRA in Bursins (VD) with SPMT

Impressive heavy-duty technology in use

As part of a challenging infrastructure project, EMIL EGGER was able to make a key contribution to the replacement of an overpass over the A1 highway between Lausanne and Geneva. The client was the Federal Roads Office FEDRO, in collaboration with Implenia Schweiz AG as the master builder.
emil-egger-spmt-verschub–2

The project was characterized by complex heavy-duty logistics, short time frames and precise coordination – with minimal disruption to traffic on the national road.

Two-part execution – two bridges, two stages

Stage 1
In a night-time operation, a 200-ton auxiliary bridge was removed in an elevated position.
Two self-propelled transport vehicles, each with 12 axle lines (SPMT Self-Propelled Modular Transporter), were used for this. The bridge was then lowered to the ground using a 350-tonne and a 300-tonne pneumatic crane and later dismantled using a 100-tonne crane.

Stage 2 (four months later)
The new UHPC bridge (ultra-high-performance concrete), weighing around 400 tons, was constructed on a falsework in an elevated position. It was then moved by 2 x 12 axle lines next to the highway, where it was moved precisely to its final position during the night. The lift to the final position was carried out using a 4-point jack-up system (hydraulic lifting system), in which each unit can carry a load of up to 250 tons.

Equipment & engineering

State-of-the-art heavy-duty equipment was used to carry out this work:

  • 4 x 6-axis line sets SPMT with 2 power packs
  • 4 jack-up units with a lifting capacity of 250 tons each
  • Tire cranes with lifting capacities of 300-350 tons
  • Auxiliary cranes up to 100 tons
  • Heavy-duty towers (up to 150 t per tower)
  • Load distribution plates to protect the substrate
  • Engineering & project coordination by EMIL EGGER

Special features

  • Extremely short closure times: The main work took place when the highway was fully closed – with time windows of less than 4 hours for the core processes.
  • Precise process planning: Every work step had to be meticulously planned and coordinated – from the positioning of the lifting systems to the coordination of the cranes and SPMT.
  • Suitable for working underneath pipes: The system is particularly well proven in a narrow construction area under existing pipes.

More news from Emil Egger

emil-egger-esk-30-spezialkran-saftpresse-9-2
EGGER special crane in use for machine insertion in the tightest of spaces
When there is no room for compromise, our ESK 30 special crane comes into play! The fully electric crane masters even tricky lifting tasks in halls and production facilities with flying colors – such as lifting a 16-ton juice press for Holderhof Sulgen AG.
Learn more
emil-egger-schwergut-kranarbeiten-pneukran-abfallanlage-99
Crane work with 650-tonne pneumatic crane for sustainable waste recycling
EMIL EGGER has developed for the operator GEVAG – SMARTE ENERGIE. FROM WASTE. – large plant components, including a filter housing with hoppers and steel fixtures. Our 650-tonne mobile crane with 38.5 m luffing jib was used.
Learn more
default
From transportation to installation – EGGER supports the bridge project in all phases
In the night of 04. The third and final major crane lift as part of the bridge replacement project in Münchenstein was successfully completed on August 5, 2025: The new underwater bridge weighing 255 tons was precisely lifted into place with a 1000-ton crawler crane at a radius of 53 meters.
Learn more
emil-egger-kranarbeiten-spezialtransport-windkraft-andermatt-47
Special transportation of wind turbines from Basel to Andermatt
Four new ENERCON wind turbines commissioned by EW Ursern and Energie Uri (EWA) for Andermatt are really getting things moving in the canton of Uri – and our team from EMIL EGGER was right in the middle of it all.
Learn more
default
Special transportation of wind turbines from Basel to Andermatt
Four new ENERCON wind turbines commissioned by EW Ursern and Energie Uri (EWA) for Andermatt are really getting things moving in the canton of Uri – and our team from EMIL EGGER was right in the middle of it all.
Learn more
emil-egger-esk-30-spezialkran-ara-thalwil-2
EGGER special crane for confined spaces
For the waste water purification plant in Thalwil, our team moved a 3.5 t clarifier screen with a radius of 18 m with millimeter precision – using our ESK 30 special crane.
Learn more
emil-egger-maschine-industrieumzug-polycontact-5
Mikron milling center safely relocated by industrial relocation team
We successfully installed a new Mikron UCP 600 Vario milling center in the basement of the company building of Polycontact AG in Chur.
Learn more
emil-egger-brueckenbau-monthey-1
Successful bridge relocation in Monthey
At the end of June, SBB reached an important milestone for the infrastructure in Monthey: the new SBB bridge over the Vièze was successfully moved – in blazing sunshine and temperatures of over 30 degrees.
Learn more
Spychertransport – Rüfenacht-Worb – Jugendarbeit Worb
EMIL EGGER moves history
In the night from Monday to Tuesday, EMIL EGGER AG was able to realize an extraordinary transport project: The approximately 250-year-old Aebersold warehouse was saved from imminent demolition and transported to its new destination at the Freizeithaus in Worb.
Learn more
emil-egger-spezialtransport-kranarbeiten-bootshaus-104101
Special transport Basel: EMIL EGGER brings 50-ton boathouse to its destination
This week, EMIL EGGER was able to realize a very special project in Basel: The transportation of the new boathouse for the emergency services of the canton of Baselland.
Learn more