Demolition work using the 450-metric-tonne mobile crane in Biel

Night-time crane operations – EMIL EGGER AG assists with the dismantling of the Heideweg Bridge

During the night of 16 to 17 June 2026, EMIL EGGER was involved in the dismantling of the Heideweg Bridge in Biel. As part of the ongoing renovation work, the central section of the bridge over Bernstrasse at the Brüggmoos junction was dismantled.
Bild 1v5

A 450-tonne mobile crane from EMIL EGGER was used for this challenging installation. The work took place during a tight night-time window and required meticulous preparation, precise coordination between all parties involved, and the utmost concentration during execution.

The Heideweg Bridge is in a poor state of repair and is therefore undergoing extensive refurbishment. The existing central section is being replaced to ensure the long-term usability of this important link. Several night-time closures were necessary to carry out the demolition work above Bernstrasse.

Special thanks go to B+S AG for their expert project support and engineering services, and to Marti AG Solothurn, the main contractor, for their professional cooperation during the construction work and the on-site demolition work.

Following the successful dismantling, the next step is already planned: the new section of the bridge will be lifted into place at a later date using a tandem lift involving a 650-tonne and a 450-tonne mobile crane from EMIL EGGER.

Projects such as these clearly demonstrate what is essential for challenging crane operations in the infrastructure sector: experience, well-rehearsed procedures, precise lifting techniques and strong collaboration between all those involved in the project.

We would like to thank all our partners and our operations team for the professional execution of this night-time crane operation.

You are currently viewing a placeholder content from YouTube. To access the actual content, click the button below. Please note that doing so will share data with third-party providers.

More Information

More news from Emil Egger

Bild 1
750-metric-ton crawler crane for the new SBB Aare Bridge in Solothurn
With cantilevers extending up to 108 meters, EMIL EGGER supported the assembly of the new steel structure for the SBB Aare Bridge in Solothurn. A total of eleven bridge elements, weighing up to 71 metric tons each, were hoisted into place.
Learn more
714026805_Biel_Heidenweg_Brücke_Einhebung_150dpi_0790_D
Tandem lift using a 650-tonne and a 450-tonne mobile crane
Following the successful dismantling in June, the next milestone in the refurbishment of the Heideweg Bridge in Biel was reached in September: the new central section of the bridge was hoisted into place over Bernstrasse at the Brüggmoos junction.
Learn more
emil-egger-bahnbrücke-wetzikon-sbb-b
LR 11000 lifts new railway bridge into place in Wetzikon
The EMIL EGGER Group’s most powerful crawler crane was deployed during the replacement of the railway bridge over Usterstrasse in Wetzikon. After lifting two abutments, each weighing 210 tonnes, the new steel bridge, weighing 160 tonnes, was precisely positioned at its intended location.
Learn more
default
1,200-tonne railway underpass in Niederbipp postponed
As part of the refurbishment of the Scharnageln–Niederbipp section of the Aare Seeland mobil AG railway line, EMIL EGGER was able to support a challenging project involving heavy-lift logistics, lifting and relocation technology.
Learn more
26-05-12-3214
Precise crane operation in winter conditions
As part of the construction of the new Säntis suspension railroad, EMIL EGGER was once again able to make a contribution to an important infrastructure project in Eastern Switzerland. Together with the fitters from Garaventa, the existing cabins of the Säntis suspension railroad were safely lifted down into the valley.
Learn more
emil-egger-reussbruecke-kranhub-thb-spezialtransporte-1
Precision in time with rail traffic
On the first weekend in May, EMIL EGGER successfully completed another important construction phase on the Reuss Bridge in Lucerne. The listed railroad bridge – over which around 200 trains pass every day – is currently being extensively renovated. The last major renovation was carried out in 1987.
Learn more
emil-egger-seftausteg-bern-4
Efficient lifting technology from EMIL EGGER for bridge renovation in Bern
The Seftau footbridge in Felsenau near Bern was successfully excavated on April 28, 2026. The 53-metre-long foot and cycle bridge connects the municipalities of Bern and Bremgarten bei Bern and is currently undergoing extensive renovation.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-22
When logistics moves mountains: EMIL EGGER brings a 1,000-tonne crane to the construction site
Before a large crawler crane even makes its first lift, an impressive logistical feat has already taken place. A crane such as the Liebherr LR 11000 is completely dismantled for transport and delivered to the construction site in numerous individual parts.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-2
Demolition of the Wallstrasse Bridge in Ulm – Video footage of the operation
A few days ago, we reported on our involvement in the demolition of the Wallstrasse Bridge in Ulm. Now, video footage provides further insights into this extraordinary project and impressively demonstrates the scale and precision of the work carried out.
Learn more
default
Heavy-lift logistics for energy infrastructure – project in Niederwil, Aargau
Since the start of the year, we have been responsible for managing all heavy-lift logistics for Regionalwerke Baden and CO2 Energie AG in connection with a new biogas processing and CO2 capture plant in Niederwil, Aargau.
Learn more