Steam turbine for Hagenholz waste incineration plant: heavy transport and single-lift installation from a single source

EMIL EGGER transports Siemens Energy turbine from Czechia to Switzerland and lifts up to 66 tonnes with precision.

We were able to make a key contribution to the expansion of the Hagenholz waste incineration plant: The new steam turbine and accessories from Siemens Energy were transported from Czechia to Switzerland by EMIL EGGER and delivered to the construction site on schedule.
_Projekt_Caliqua-13

The components were unloaded using a 300-tonne pneumatic crane and lifted into position using a 500-tonne lifting system and a long head beam. The heaviest single component – the main turbine – weighed 66 tonnes.

As the general contractor, Caliqua is responsible for the turnkey expansion of the energy centre. Its scope of supply includes, among other things:

  • a extraction back-pressure turbine with 10 MW generator output
  • an air-cooled condenser
  • a heating condenser for district heating
  • and all necessary ancillary systems

As a specialist in thermal plants, Caliqua implements sustainable energy centres, combined heat and power plants and district heating systems – from the initial concept to the finished plant.

Together, we are contributing to the energy future of the canton of Zurich:
With the third incineration line, the Hagenholz waste incineration plant will increase its capacity, efficiency and production of electricity and district heating in the future – an important step in view of growing waste volumes and rising energy needs.

In the video: Our heavy assembly work for the new turbine plant.

YouTube

By loading the video, you agree to YouTube's privacy policy.
Learn more

Load video

More news from Emil Egger

emil-egger-reussbruecke-kranhub-thb-spezialtransporte-1
Precision in time with rail traffic
On the first weekend in May, EMIL EGGER successfully completed another important construction phase on the Reuss Bridge in Lucerne. The listed railroad bridge – over which around 200 trains pass every day – is currently being extensively renovated. The last major renovation was carried out in 1987.
Learn more
emil-egger-seftausteg-bern-4
Efficient lifting technology from EMIL EGGER for bridge renovation in Bern
The Seftau footbridge in Felsenau near Bern was successfully excavated on April 28, 2026. The 53-metre-long foot and cycle bridge connects the municipalities of Bern and Bremgarten bei Bern and is currently undergoing extensive renovation.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-22
When logistics moves mountains: EMIL EGGER brings a 1,000-tonne crane to the construction site
Before a large crawler crane even makes its first lift, an impressive logistical feat has already taken place. A crane such as the Liebherr LR 11000 is completely dismantled for transport and delivered to the construction site in numerous individual parts.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-2
Demolition of the Wallstrasse Bridge in Ulm – Video footage of the operation
A few days ago, we reported on our involvement in the demolition of the Wallstrasse Bridge in Ulm. Now, video footage provides further insights into this extraordinary project and impressively demonstrates the scale and precision of the work carried out.
Learn more
default
Heavy-lift logistics for energy infrastructure – project in Niederwil, Aargau
Since the start of the year, we have been responsible for managing all heavy-lift logistics for Regionalwerke Baden and CO2 Energie AG in connection with a new biogas processing and CO2 capture plant in Niederwil, Aargau.
Learn more
Projekt SAW-3
EMIL EGGER lifts 56-tonne girders with millimeter precision
Our team was able to accompany a demanding precision lift on the Seedammcenter project in Pfäffikon SZ: A 56-tonne girder was positioned together with other concrete elements with millimetre precision. A 450-tonne pneumatic crane from EMIL EGGER was used for this work, which lifted the heavy components safely and in a controlled manner to their intended position.
Learn more
Rückbau der westlichen Wallstrassenbrücke in Ulm (1)
LR 11000 heavy-duty crane lifts up to 500 t bridge segments
As part of the comprehensive renewal of the B10 in Ulm, the Wallstrasse bridge is being completely replaced. With an investment volume of over 200 million euros, the infrastructure project is one of the largest transportation projects in the region and will take several years to complete.
Learn more
emil-egger-industrieumzug-energietechnik-a
Machine installation and assembly for the energy transition
EMIL EGGER carries out demanding machine installation and assembly work for the energy infrastructure. Two heat accumulators and two cold accumulators were installed and assembled safely, precisely and on schedule.
Learn more
emil-egger-esk-30-spezialkran-saftpresse-9-2
EGGER special crane in use for machine insertion in the tightest of spaces
When there is no room for compromise, our ESK 30 special crane comes into play! The fully electric crane masters even tricky lifting tasks in halls and production facilities with flying colors – such as lifting a 16-ton juice press for Holderhof Sulgen AG.
Learn more
emil-egger-schwergut-kranarbeiten-pneukran-abfallanlage-99
Crane work with 650-tonne pneumatic crane for sustainable waste recycling
EMIL EGGER has developed for the operator GEVAG – SMARTE ENERGIE. FROM WASTE. – large plant components, including a filter housing with hoppers and steel fixtures. Our 650-tonne mobile crane with 38.5 m luffing jib was used.
Learn more