before 1 year | EMIL EGGER AG

Dismantling of the B43 bridge over the DB facilities in Hanau

Crane work with our 750-ton crawler crane

Work began on December 2, 2024 and is scheduled to be completed by March 2025. The first construction phase had its intensive phase in the last week of December. The second intensive phase will now follow over the next few weeks.
1emil-egger-rueckbau-bruecke-hanau-raupenkran-2025-19

For dismantling, the bridge superstructure is first divided into segments using sawing technology. The bridge sections are then lifted out safely and precisely using a pneumatic and crawler crane.

In order to ensure safety during the work, column supports are being installed in advance to secure the pendulum columns, additional position stabilizers for the superstructure and support towers.

The existing prestressed concrete bridge with a total length of 120 meters will be dismantled mainly during rail closure breaks and in 24-hour operation in order to keep disruptions to rail traffic to a minimum. A particular challenge here is the limited movement space of the large cranes due to the adjacent railroad lines.

Photography and aerial photography service Jan R. Schäfer

More news from Emil Egger

emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-22
When logistics moves mountains: EMIL EGGER brings a 1,000-tonne crane to the construction site
Before a large crawler crane even makes its first lift, an impressive logistical feat has already taken place. A crane such as the Liebherr LR 11000 is completely dismantled for transport and delivered to the construction site in numerous individual parts.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-2
Demolition of the Wallstrasse Bridge in Ulm – Video footage of the operation
A few days ago, we reported on our involvement in the demolition of the Wallstrasse Bridge in Ulm. Now, video footage provides further insights into this extraordinary project and impressively demonstrates the scale and precision of the work carried out.
Learn more
default
Heavy-lift logistics for energy infrastructure – project in Niederwil, Aargau
Since the start of the year, we have been responsible for managing all heavy-lift logistics for Regionalwerke Baden and CO2 Energie AG in connection with a new biogas processing and CO2 capture plant in Niederwil, Aargau.
Learn more
Projekt SAW-3
EMIL EGGER lifts 56-tonne girders with millimeter precision
Our team was able to accompany a demanding precision lift on the Seedammcenter project in Pfäffikon SZ: A 56-tonne girder was positioned together with other concrete elements with millimetre precision. A 450-tonne pneumatic crane from EMIL EGGER was used for this work, which lifted the heavy components safely and in a controlled manner to their intended position.
Learn more
Rückbau der westlichen Wallstrassenbrücke in Ulm (1)
LR 11000 heavy-duty crane lifts up to 500 t bridge segments
As part of the comprehensive renewal of the B10 in Ulm, the Wallstrasse bridge is being completely replaced. With an investment volume of over 200 million euros, the infrastructure project is one of the largest transportation projects in the region and will take several years to complete.
Learn more
emil-egger-industrieumzug-energietechnik-a
Machine installation and assembly for the energy transition
EMIL EGGER carries out demanding machine installation and assembly work for the energy infrastructure. Two heat accumulators and two cold accumulators were installed and assembled safely, precisely and on schedule.
Learn more
_Projekt_Caliqua-13
Steam turbine for Hagenholz waste incineration plant: heavy transport and single-lift installation from a single source
We were able to make a key contribution to the expansion of the Hagenholz waste incineration plant: The new steam turbine and accessories from Siemens Energy were transported from Czechia to Switzerland by EMIL EGGER and delivered to the construction site on schedule.
Learn more
ChatGPT Image 22. Dez. 2025, 11_25_06
EMIL EGGER transports 30 construction machines from Langenthal to Baar
We transported a total of 30 construction machines from Langenthal to Baar for Gebrüder Hodel AG – spread over 11 loads, all carried out with the same articulated lorry.
Learn more
emil-egger-esk-30-spezialkran-saftpresse-9-2
EGGER special crane in use for machine insertion in the tightest of spaces
When there is no room for compromise, our ESK 30 special crane comes into play! The fully electric crane masters even tricky lifting tasks in halls and production facilities with flying colors – such as lifting a 16-ton juice press for Holderhof Sulgen AG.
Learn more
emil-egger-schwergut-kranarbeiten-pneukran-abfallanlage-99
Crane work with 650-tonne pneumatic crane for sustainable waste recycling
EMIL EGGER has developed for the operator GEVAG – SMARTE ENERGIE. FROM WASTE. – large plant components, including a filter housing with hoppers and steel fixtures. Our 650-tonne mobile crane with 38.5 m luffing jib was used.
Learn more