before 1 month | EMIL EGGER AG

When logistics moves mountains: EMIL EGGER brings a 1,000-tonne crane to the construction site

Assembly of a Liebherr LR 11000: Transport, assembly and logistics explained

Before a large crawler crane even makes its first lift, an impressive logistical feat has already taken place. A crane such as the Liebherr LR 11000 is completely dismantled for transport and delivered to the construction site in numerous individual parts.
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-22

Up to 30–40 lorry lads are required to deliver all the components – including crawler tracks, the slewing platform, boom sections, counterweights and accessories.

Individual parts weigh up to around 60 tonnes.

The actual assembly then begins on site:

  • Assembly of the crawler tracks and slewing platform
  • Assembly of the counterweights and derrick system
  • Installation of the winches and drive units
  • Step-by-step erection of the main boom
  • Safety checks and fine-tuning

Depending on the configuration, the complete erection takes around 3 to 5 days – and requires a well-coordinated team and precise planning.

Only then is the crane ready for its actual task:

Moving heavy loads weighing several hundred tonnes with millimetre precision. Large cranes take centre stage on the construction site – yet even their assembly is a logistical heavyweight.

Pictures: photo.voelter.de / Markus Voelter Photography

More news from Emil Egger

emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-2
Demolition of the Wallstrasse Bridge in Ulm – Video footage of the operation
A few days ago, we reported on our involvement in the demolition of the Wallstrasse Bridge in Ulm. Now, video footage provides further insights into this extraordinary project and impressively demonstrates the scale and precision of the work carried out.
Learn more
default
Heavy-lift logistics for energy infrastructure – project in Niederwil, Aargau
Since the start of the year, we have been responsible for managing all heavy-lift logistics for Regionalwerke Baden and CO2 Energie AG in connection with a new biogas processing and CO2 capture plant in Niederwil, Aargau.
Learn more
Projekt SAW-3
EMIL EGGER lifts 56-tonne girders with millimeter precision
Our team was able to accompany a demanding precision lift on the Seedammcenter project in Pfäffikon SZ: A 56-tonne girder was positioned together with other concrete elements with millimetre precision. A 450-tonne pneumatic crane from EMIL EGGER was used for this work, which lifted the heavy components safely and in a controlled manner to their intended position.
Learn more
Rückbau der westlichen Wallstrassenbrücke in Ulm (1)
LR 11000 heavy-duty crane lifts up to 500 t bridge segments
As part of the comprehensive renewal of the B10 in Ulm, the Wallstrasse bridge is being completely replaced. With an investment volume of over 200 million euros, the infrastructure project is one of the largest transportation projects in the region and will take several years to complete.
Learn more
emil-egger-industrieumzug-energietechnik-a
Machine installation and assembly for the energy transition
EMIL EGGER carries out demanding machine installation and assembly work for the energy infrastructure. Two heat accumulators and two cold accumulators were installed and assembled safely, precisely and on schedule.
Learn more
_Projekt_Caliqua-13
Steam turbine for Hagenholz waste incineration plant: heavy transport and single-lift installation from a single source
We were able to make a key contribution to the expansion of the Hagenholz waste incineration plant: The new steam turbine and accessories from Siemens Energy were transported from Czechia to Switzerland by EMIL EGGER and delivered to the construction site on schedule.
Learn more
emil-egger-esk-30-spezialkran-saftpresse-9-2
EGGER special crane in use for machine insertion in the tightest of spaces
When there is no room for compromise, our ESK 30 special crane comes into play! The fully electric crane masters even tricky lifting tasks in halls and production facilities with flying colors – such as lifting a 16-ton juice press for Holderhof Sulgen AG.
Learn more
emil-egger-schwergut-kranarbeiten-pneukran-abfallanlage-99
Crane work with 650-tonne pneumatic crane for sustainable waste recycling
EMIL EGGER has developed for the operator GEVAG – SMARTE ENERGIE. FROM WASTE. – large plant components, including a filter housing with hoppers and steel fixtures. Our 650-tonne mobile crane with 38.5 m luffing jib was used.
Learn more
ohne-Rahmen-1-1
EMIL EGGER lifts 190 t underpass in Rheinfelden
The old SBB underpass “Büchliweg” was lifted with a stacking system (jack-up system) and moved out directly on self-propelled modular transporters (SPMT) and deposited in an interim storage area.
Learn more