Replacement beaver bridge in Biberbrugg with 1000 tons crane

17 m long and 240 tons heavy bridge moved with LR 11000

Numerous onlookers followed the work of replacing the 60-year-old beaver bridge in Biberbrugg from September 30 to October 2. Toneatti AG, together with subcontractors such as EMIL EGGER, carried out the long-planned work. After dismantling the old bridge, the new one, 17 m long and weighing 240 tons, was then set with millimeter precision.
emil-egger-crane-work-moving-railway-bridge

Some preliminary work was necessary for this king stage of the construction project. Floor slabs under the beaver, abutment and wing walls, and the crane foundation were constructed. The large, red, imposing crawler crane was delivered by 40 trucks.

YouTube

By loading the video, you agree to YouTube's privacy policy.
Learn more

Load video

Professional Crane logistics

EMIL EGGER ranks in the top 20 of German-speaking crane service providers

Fast, flexible and professional – that’s our motto. We can be reached 24 hours on the hotline +41 71 282 52 20 and are available in all regions of Switzerland. Thanks to our powerful crane and special transport sector, we are always ready for action. EMIL EGGER is also the only Swiss company to rank among the top 20 German-speaking crane service providers. Our diverse fleet includes mobile cranes, crawler cranes, mobile construction cranes, special cranes, truck cranes and mini cranes.

Crane logistics

More news from Emil Egger

emil-egger-muttenz-überfuehrung-kranarbeiten-2
Successful dismantling weekend in Muttenz
Last weekend we were able to complete the crane work for the dismantling of the Grenzacherstrasse overpass in Muttenz.
Learn more
emil-egger-tunnelbohrmaschine-gotthardtunnel-spezialtransport 5
Special transportation of large and heavy parts of a tunnel boring machine
Last week, EMIL EGGER AG delivered two of the largest and heaviest parts of the tunnel boring machine for the second tube of the Gotthard tunnel.
Learn more
default
Work of art installed in Zurich Werdhölzli
The artwork “Schräg im Gleichgewicht” was created in 1984. It was dismantled in 2014 for the renovation of the entrance area and temporarily stored at Werdhölzli.
Learn more
default
Crane hand in action with the special crane from EMIL EGGER
We had the exciting task of moving the façade supports with our special ESK 30 crane and the attached crane hand with millimeter precision on a nearly completed building.
Learn more
emil-egger-muttenz-freulerbruecke-5
Dismantling of Freuler Bridge Muttenz
In the night from 8 to July 9, the first stage of the crane work for the dismantling of the Freuler Bridge came to an end in Muttenz.
Learn more
emil-egger-kornwestheim-brueckenbau-6
Swiss 1000 t crawler crane lifts bridge sections in the greater Stuttgart area
At the beginning of May, we were involved in the dismantling of the “Great Pflugfelder Bridge” in Kornwestheim. The truss bridge dates back to 1917 and crosses the tracks of an important shunting and transhipment yard in the greater Stuttgart area.
Learn more
emil-egger-industrieumzug-maschinentransport-4
Industrial relocation team in action for Allegra Passugger Mineralquellen AG
Our industrial relocation team recently had the task of temporarily storing, transporting, lifting and positioning a bottle washing and filling system for Allegra Passugger Mineralquellen AG.
Learn more
emil-egger-basel-terminal-rheinhafen-kleinhuenigen-2
Efficient construction site logistics
Rhenus Port Logistics is investing in a new transshipment terminal in the Rhine port of Basel-Kleinhünigen. EMIL EGGER was entrusted with the logistics of the prefabricated concrete elements.
Learn more
emil-egger-hawker-hunter-aviation-transport-21
The Hawker Hunter aeroplane is safely back at the Hunter association Obersimmental
Until a few years ago, the former Hunter fighter aircraft of the Swiss Air Force were among the highlights at airshows in Switzerland. So was the Papyrus Hunter. The jet has been looked after and maintained by the Hunter association Obersimmental for many years. Unfortunately, the increasingly strict regulations became its downfall. In autumn 2023, the Papyrus was flown over to Altenrhein for its annual inspection. It was no longer allowed to take off from there.
Learn more
default
New logistics center in Härkingen
The EMIL EGGER Group’s new logistics center in Härkingen is now complete. With a length of 120 metres and a width of 62 metres, the building has impressive dimensions and offers us and our customers particular flexibility and new possibilities.
Learn more