From transportation to installation – EGGER supports the bridge project in all phases

Millimeter-precise bridge assembly in Münchenstein - lifting in with LR 11000

In the night of 04. The third and final major crane lift as part of the bridge replacement project in Münchenstein was successfully completed on August 5, 2025: The new underwater bridge weighing 255 tons was precisely lifted into place with a 1000-ton crawler crane at a radius of 53 meters.
default

The work was carried out in extremely confined spaces and under complex conditions in the area of underground and adjacent infrastructure facilities – a particular challenge for planning and execution.

Review: The previous missions

The crawler crane had already been used for key work steps in the previous months:

  • June 2024
    Dismantling of the existing upper water bridge
    Moving the new upper water bridge onto the prepared shunting track
  • February 2025
    Dismantling of the existing underwater bridge

Further services by EMIL EGGER

In addition to the crane work, EMIL EGGER was also responsible for extensive additional services:

  • Special transports of the new bridge sections with widths of over 6 meters
  • Crane work during unloading, assembly and installation at the installation site
  • Dismantling work on the old bridge sections including loading and removal

Together to success

We would like to sincerely thank our client and the building owner for the trusting and successful cooperation. This project is another example of how complex tasks can be mastered with precision, experience and teamwork.

You are currently viewing a placeholder content from YouTube. To access the actual content, click the button below. Please note that doing so will share data with third-party providers.

More Information

More news from Emil Egger

emil-egger-bahnbrücke-wetzikon-sbb-b
LR 11000 lifts new railway bridge into place in Wetzikon
The EMIL EGGER Group’s most powerful crawler crane was deployed during the replacement of the railway bridge over Usterstrasse in Wetzikon. After lifting two abutments, each weighing 210 tonnes, the new steel bridge, weighing 160 tonnes, was precisely positioned at its intended location.
Learn more
default
1,200-tonne railway underpass in Niederbipp postponed
As part of the refurbishment of the Scharnageln–Niederbipp section of the Aare Seeland mobil AG railway line, EMIL EGGER was able to support a challenging project involving heavy-lift logistics, lifting and relocation technology.
Learn more
emil-egger-spezialtransport-säntis-schwebebahn-1
Construction of the new Säntis cable car
The first cables for the new Säntisbahn have arrived at Schwägalp – and we were able to play a part in this special transport operation.
Learn more
emil-egger-transport-flugzeug-cellsius-4
EMIL EGGER transports the H2-Sling hydrogen-powered aircraft
For the Swiss innovation project CELLSIUS Aero, EMIL EGGER was entrusted with an extraordinary transport mission: The H2-Sling, a hydrogen-powered experimental aircraft, was transported from Dübendorf to Payerne.
Learn more
26-05-12-3214
Precise crane operation in winter conditions
As part of the construction of the new Säntis suspension railroad, EMIL EGGER was once again able to make a contribution to an important infrastructure project in Eastern Switzerland. Together with the fitters from Garaventa, the existing cabins of the Säntis suspension railroad were safely lifted down into the valley.
Learn more
emil-egger-reussbruecke-kranhub-thb-spezialtransporte-1
Precision in time with rail traffic
On the first weekend in May, EMIL EGGER successfully completed another important construction phase on the Reuss Bridge in Lucerne. The listed railroad bridge – over which around 200 trains pass every day – is currently being extensively renovated. The last major renovation was carried out in 1987.
Learn more
emil-egger-seftausteg-bern-4
Efficient lifting technology from EMIL EGGER for bridge renovation in Bern
The Seftau footbridge in Felsenau near Bern was successfully excavated on April 28, 2026. The 53-metre-long foot and cycle bridge connects the municipalities of Bern and Bremgarten bei Bern and is currently undergoing extensive renovation.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-22
When logistics moves mountains: EMIL EGGER brings a 1,000-tonne crane to the construction site
Before a large crawler crane even makes its first lift, an impressive logistical feat has already taken place. A crane such as the Liebherr LR 11000 is completely dismantled for transport and delivered to the construction site in numerous individual parts.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-2
Demolition of the Wallstrasse Bridge in Ulm – Video footage of the operation
A few days ago, we reported on our involvement in the demolition of the Wallstrasse Bridge in Ulm. Now, video footage provides further insights into this extraordinary project and impressively demonstrates the scale and precision of the work carried out.
Learn more
default
Heavy-lift logistics for energy infrastructure – project in Niederwil, Aargau
Since the start of the year, we have been responsible for managing all heavy-lift logistics for Regionalwerke Baden and CO2 Energie AG in connection with a new biogas processing and CO2 capture plant in Niederwil, Aargau.
Learn more