Precision and teamwork for machine relocation in Künten

Special heavy goods logistics challenge for industrial relocation

For the packaging and molded parts manufacturer Taracell AG in Künten, we mastered a challenging heavy goods logistics task.
emil-egger-industrieumzug-schwergut-logistik-maschine

Thanks to our experienced industrial relocation team, the three new Teubert machines and the mold tool changer were installed safely and efficiently.

A total of 132 tons of dismantled equipment was brought in through the roof. The respective main bodies of the three machines weighed 26 tons each.

The major challenge here was the limited room height due to the sloping roof beams.

A big thank you to Taracell AG for the special order and to our team for the calm, precise and speedy implementation!

YouTube

By loading the video, you agree to YouTube's privacy policy.
Learn more

Load video

More news from Emil Egger

emil-egger-bahnbrücke-wetzikon-sbb-b
LR 11000 lifts new railway bridge into place in Wetzikon
The EMIL EGGER Group’s most powerful crawler crane was deployed during the replacement of the railway bridge over Usterstrasse in Wetzikon. After lifting two abutments, each weighing 210 tonnes, the new steel bridge, weighing 160 tonnes, was precisely positioned at its intended location.
Learn more
default
1,200-tonne railway underpass in Niederbipp postponed
As part of the refurbishment of the Scharnageln–Niederbipp section of the Aare Seeland mobil AG railway line, EMIL EGGER was able to support a challenging project involving heavy-lift logistics, lifting and relocation technology.
Learn more
emil-egger-spezialtransport-säntis-schwebebahn-1
Construction of the new Säntis cable car
The first cables for the new Säntisbahn have arrived at Schwägalp – and we were able to play a part in this special transport operation.
Learn more
emil-egger-transport-flugzeug-cellsius-4
EMIL EGGER transports the H2-Sling hydrogen-powered aircraft
For the Swiss innovation project CELLSIUS Aero, EMIL EGGER was entrusted with an extraordinary transport mission: The H2-Sling, a hydrogen-powered experimental aircraft, was transported from Dübendorf to Payerne.
Learn more
26-05-12-3214
Precise crane operation in winter conditions
As part of the construction of the new Säntis suspension railroad, EMIL EGGER was once again able to make a contribution to an important infrastructure project in Eastern Switzerland. Together with the fitters from Garaventa, the existing cabins of the Säntis suspension railroad were safely lifted down into the valley.
Learn more
emil-egger-reussbruecke-kranhub-thb-spezialtransporte-1
Precision in time with rail traffic
On the first weekend in May, EMIL EGGER successfully completed another important construction phase on the Reuss Bridge in Lucerne. The listed railroad bridge – over which around 200 trains pass every day – is currently being extensively renovated. The last major renovation was carried out in 1987.
Learn more
emil-egger-seftausteg-bern-4
Efficient lifting technology from EMIL EGGER for bridge renovation in Bern
The Seftau footbridge in Felsenau near Bern was successfully excavated on April 28, 2026. The 53-metre-long foot and cycle bridge connects the municipalities of Bern and Bremgarten bei Bern and is currently undergoing extensive renovation.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-22
When logistics moves mountains: EMIL EGGER brings a 1,000-tonne crane to the construction site
Before a large crawler crane even makes its first lift, an impressive logistical feat has already taken place. A crane such as the Liebherr LR 11000 is completely dismantled for transport and delivered to the construction site in numerous individual parts.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-2
Demolition of the Wallstrasse Bridge in Ulm – Video footage of the operation
A few days ago, we reported on our involvement in the demolition of the Wallstrasse Bridge in Ulm. Now, video footage provides further insights into this extraordinary project and impressively demonstrates the scale and precision of the work carried out.
Learn more
default
Heavy-lift logistics for energy infrastructure – project in Niederwil, Aargau
Since the start of the year, we have been responsible for managing all heavy-lift logistics for Regionalwerke Baden and CO2 Energie AG in connection with a new biogas processing and CO2 capture plant in Niederwil, Aargau.
Learn more