before 2 weeks | EMIL EGGER AG

New logistics center in Härkingen

Expanded capacities for the storage of heavy goods and general cargo

The EMIL EGGER Group's new logistics center in Härkingen is now complete. With a length of 120 metres and a width of 62 metres, the building has impressive dimensions and offers us and our customers particular flexibility and new possibilities.
default

The logistics center comprises:

  • A basement with parking spaces for 180 cars and a corresponding number of e-charging stations.
  • A ground floor with a 3,100 m² heavy goods warehouse, equipped with one 32-tonne and three 16-tonne indoor cranes, which facilitate the storage and retrieval of large and heavy goods.
  • A goods handling area covering 4,100 m² with a total of 10 loading ramps and five 10-tonne overhead cranes.
  • Three floors with a combination of office and warehouse space, totalling over 10,000 m² of storage space.
  • In addition, we have installed a photovoltaic system on the large roof area, which covers part of our electricity requirements. Our ETE warehouse team has now moved into the 2nd floor as a new workplace, where training rooms, recreation rooms, bunks and cloakrooms have also been set up.

Thanks to the prefabricated concrete components, the building shell was completed in just 13 months. The heaviest components, weighing up to 35 tonnes, were assembled efficiently using our 750 tonne crawler crane.

We are proud of our team and everyone involved in making this fantastic project possible!

YouTube

By loading the video, you agree to YouTube's privacy policy.
Learn more

Load video

More news from Emil Egger

emil-egger-basel-terminal-rheinhafen-kleinhuenigen-2
Efficient construction site logistics
Rhenus Port Logistics is investing in a new transshipment terminal in the Rhine port of Basel-Kleinhünigen. EMIL EGGER was entrusted with the logistics of the prefabricated concrete elements.
Learn more
emil-egger-hawker-hunter-aviation-transport-21
The Hawker Hunter aeroplane is safely back at the Hunter association Obersimmental
Until a few years ago, the former Hunter fighter aircraft of the Swiss Air Force were among the highlights at airshows in Switzerland. So was the Papyrus Hunter. The jet has been looked after and maintained by the Hunter association Obersimmental for many years. Unfortunately, the increasingly strict regulations became its downfall. In autumn 2023, the Papyrus was flown over to Altenrhein for its annual inspection. It was no longer allowed to take off from there.
Learn more
emil-egger-jungfrau-bahn-transport-zug (1 von 1)
Spectacular transportation
Tight curves, steep paths – a special transporter brings a new train of the Lauterbrunnen-Mürren mountain railroad to Winteregg.
Learn more
emil-egger-wagon-funicular-crane-logistics-special-transport 1974
Historic moment
After the last trip on Easter Monday, the funicular carriages were lifted off the rails. Back in 1974, as today, EMIL EGGER took care of the logistics.
Learn more
emil-egger-bridge-lifting-crane-work-pneu-crane-sitterbridge-5
Crane specialist EGGER takes over bridge lift
Two hours of work in around one minute: the 120-year-old Sitter Bridge is excavated for the first time for extensive renovation work. This measure is part of the renewal of the railroad line between Gais and Appenzell.
Learn more
emil-egger-ms-yellow-schiffstransport
MS Yellow is transported from Lake Zug to Lake Biel
The passenger ship MS Yellow was transported from Zug to Sugiez by EMIL EGGER using heavy goods transport.
Learn more
prix_svc_ostschweiz-5860-20240307
Prix SVC Eastern Switzerland: Five companies were in the final for the 2024 award
The final for the “Prix SVC Ostschweiz” took place on March 7. For the eleventh time, the Swiss Venture Club (SVC) is honoring exemplary small and medium-sized enterprises (SMEs). Marco Fritsche hosted the award ceremony in the Olma exhibition halls. The event offered the 900 invited guests from business, science, politics and the media insights into entrepreneurship in the region.
Learn more
emil-egger-stahlbruecke-hub-muttenz
Successful lifting of a reinforced concrete composite bridge in Muttenz
In the night from 15. on the On January 16, as part of the repair work on the Grenzacher Bridge in Muttenz, we were able to lift the new 275 t, 50 m long reinforced concrete composite bridge over the N02 freeway using our 750 t crawler crane. Thanks to our modern equipment, it is possible to handle such unique load cases with this category of crane.
Learn more
emil-egger-special-transport-train-car-2
Stadler Rail Transport
Last week we had the pleasure of transporting a railcar box from St. Margrethen to Dresden for our customer Stadler Rail.
Learn more
emil-egger-mining-excavator-800-ton-special-transport-crane-work-65
Exhibit for the new Heavy Metal Garden in Appenzellerpark
Seventh largest mining excavator in the world weighing 800 tons transported from Birsfelden to Herisau.