before 2 months | EMIL EGGER AG

EMIL EGGER moves history

250 years old Aebersold warehouse moves from Rüfenacht to Worb

In the night from Monday to Tuesday, EMIL EGGER AG was able to realize an extraordinary transport project: The approximately 250-year-old Aebersold warehouse was saved from imminent demolition and transported to its new destination at the Freizeithaus in Worb.
Spychertransport – Rüfenacht-Worb – Jugendarbeit Worb

The historic warehouse – weighing around ten tons and almost eight metres wide and high – was moved from Rüfenacht to Worb. With an experienced team, a pneumatic crane and a low-bed trailer, we lifted the granary safely from its foundations, transported it and positioned it at its new location

“Our aim was not just to move technology, but history.

– Dominik Rufer, Project Manager at EMIL EGGER AG

We would like to thank all partners involved – in particular the client Holzbau Partner AG, Eberhart Holzbau, but also the Worb youth work and those responsible for preserving this piece of history Marco Jorio (President of IG Worber Geschichte), Jonathan Gimmel (President of the Board of Trustees of the Bern Art Museum and the Paul Klee Center and President of the Worb youth work) – for the smooth cooperation. Together, we have helped to preserve a piece of Swiss building culture for future generations.

Photo/video: Dersu Huber / dersu.ch / Provided by Jugendarbeit Worb

You can find out more about our special transportation services under: Special transports

YouTube

By loading the video, you agree to YouTube's privacy policy.
Learn more

Load video

More news from Emil Egger

emil-egger-maschine-industrieumzug-polycontact-5
Mikron milling center safely relocated by industrial relocation team
We successfully installed a new Mikron UCP 600 Vario milling center in the basement of the company building of Polycontact AG in Chur.
Learn more
emil-egger-brueckenbau-monthey-1
Successful bridge relocation in Monthey
At the end of June, SBB reached an important milestone for the infrastructure in Monthey: the new SBB bridge over the Vièze was successfully moved – in blazing sunshine and temperatures of over 30 degrees.
Learn more
emil-egger-spezialtransport-kranarbeiten-bootshaus-104101
Special transport Basel: EMIL EGGER brings 50-ton boathouse to its destination
This week, EMIL EGGER was able to realize a very special project in Basel: The transportation of the new boathouse for the emergency services of the canton of Baselland.
Learn more
emil-egger-spmt-verschub–2
Efficient bridge replacement for the ASTRA in Bursins (VD) with SPMT
As part of a challenging infrastructure project, EMIL EGGER was able to make a key contribution to the replacement of an overpass over the A1 highway between Lausanne and Geneva. The client was the Federal Roads Office FEDRO, in collaboration with Implenia Schweiz AG as the master builder.
Learn more
schoenausteg-kranlogistik-emil-egger
Popular Schönausteg in Bern back in its old place
Last Monday morning, we were able to accompany a very special moment with our crane logistics: After several months of renovation, the listed Schönausteg in Bern was lifted back into its original position above the River Aare.
Learn more
1emil-egger-elektro-baustelle-lkw-bagger-6
EMIL EGGER on the road electrically
With the “e-construction site” project, the city of Zurich is pursuing the goal of testing the use of electrically powered construction site vehicles in order to reduce greenhouse gas and noise emissions and improve air quality.
Learn more
default
Successful reinstallation of the Sitter Bridge in Appenzell
EMIL EGGER at work on a challenging infrastructure project for Appenzeller Bahnen.
Learn more
default
185 tons of Reuss bridge on the hook
On the weekend of 22/23 March 2025, a significant milestone was reached in the renovation of the Reussbrücke Fluhmühle bridge in Lucerne: the first of three bridge sections was successfully lifted out – an impressive 185 tons of steel were suspended from the 1000 t crawler crane with an 84 m jib!
Learn more
emil-egger-industrieumzug-schwergut-logistik-maschine
Precision and teamwork for machine relocation in Künten
For the packaging and molded parts manufacturer Taracell AG in Künten, we mastered a challenging heavy goods logistics task.
Learn more
1emil-egger-rueckbau-bruecke-hanau-raupenkran-2025-19
Dismantling of the B43 bridge over the DB facilities in Hanau
Work began on December 2, 2024 and is scheduled to be completed by March 2025. The first construction phase had its intensive phase in the last week of December. The second intensive phase will now follow over the next few weeks.
Learn more