Successful lifting of a reinforced concrete composite bridge in Muttenz

Night operation for crane work

In the night from 15. on the On January 16, as part of the repair work on the Grenzacher Bridge in Muttenz, we were able to lift the new 275 t, 50 m long reinforced concrete composite bridge over the N02 freeway using our 750 t crawler crane. Thanks to our modern equipment, it is possible to handle such unique load cases with this category of crane.
emil-egger-stahlbruecke-hub-muttenz

For EMIL EGGER AG, this assignment marks the completion of the N02 bridge replacement sub-project, in which we were already involved in the dismantling of the existing bridge in the fall of 2023 and were able to carry out the transport and crane work for the assembly of the steel structure.

Construction work on the bridge should be completed by the end of March this year so that the other bridge sections over the SBB track field can be replaced.

We would like to thank the project partners involved for their successful cooperation.

YouTube

By loading the video, you agree to YouTube's privacy policy.
Learn more

Load video

More news from Emil Egger

26-05-12-3214
Precise crane operation in winter conditions
As part of the construction of the new Säntis suspension railroad, EMIL EGGER was once again able to make a contribution to an important infrastructure project in Eastern Switzerland. Together with the fitters from Garaventa, the existing cabins of the Säntis suspension railroad were safely lifted down into the valley.
Learn more
emil-egger-reussbruecke-kranhub-thb-spezialtransporte-1
Precision in time with rail traffic
On the first weekend in May, EMIL EGGER successfully completed another important construction phase on the Reuss Bridge in Lucerne. The listed railroad bridge – over which around 200 trains pass every day – is currently being extensively renovated. The last major renovation was carried out in 1987.
Learn more
emil-egger-seftausteg-bern-4
Efficient lifting technology from EMIL EGGER for bridge renovation in Bern
The Seftau footbridge in Felsenau near Bern was successfully excavated on April 28, 2026. The 53-metre-long foot and cycle bridge connects the municipalities of Bern and Bremgarten bei Bern and is currently undergoing extensive renovation.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-22
When logistics moves mountains: EMIL EGGER brings a 1,000-tonne crane to the construction site
Before a large crawler crane even makes its first lift, an impressive logistical feat has already taken place. A crane such as the Liebherr LR 11000 is completely dismantled for transport and delivered to the construction site in numerous individual parts.
Learn more
emil-egger-rueckbau-wallstrassenbruecke-ulm-lr11000-2
Demolition of the Wallstrasse Bridge in Ulm – Video footage of the operation
A few days ago, we reported on our involvement in the demolition of the Wallstrasse Bridge in Ulm. Now, video footage provides further insights into this extraordinary project and impressively demonstrates the scale and precision of the work carried out.
Learn more
default
Heavy-lift logistics for energy infrastructure – project in Niederwil, Aargau
Since the start of the year, we have been responsible for managing all heavy-lift logistics for Regionalwerke Baden and CO2 Energie AG in connection with a new biogas processing and CO2 capture plant in Niederwil, Aargau.
Learn more
Projekt SAW-3
EMIL EGGER lifts 56-tonne girders with millimeter precision
Our team was able to accompany a demanding precision lift on the Seedammcenter project in Pfäffikon SZ: A 56-tonne girder was positioned together with other concrete elements with millimetre precision. A 450-tonne pneumatic crane from EMIL EGGER was used for this work, which lifted the heavy components safely and in a controlled manner to their intended position.
Learn more
Rückbau der westlichen Wallstrassenbrücke in Ulm (1)
LR 11000 heavy-duty crane lifts up to 500 t bridge segments
As part of the comprehensive renewal of the B10 in Ulm, the Wallstrasse bridge is being completely replaced. With an investment volume of over 200 million euros, the infrastructure project is one of the largest transportation projects in the region and will take several years to complete.
Learn more
emil-egger-industrieumzug-energietechnik-a
Machine installation and assembly for the energy transition
EMIL EGGER carries out demanding machine installation and assembly work for the energy infrastructure. Two heat accumulators and two cold accumulators were installed and assembled safely, precisely and on schedule.
Learn more
_Projekt_Caliqua-13
Steam turbine for Hagenholz waste incineration plant: heavy transport and single-lift installation from a single source
We were able to make a key contribution to the expansion of the Hagenholz waste incineration plant: The new steam turbine and accessories from Siemens Energy were transported from Czechia to Switzerland by EMIL EGGER and delivered to the construction site on schedule.
Learn more